WIKA INSTRUMENTS
Goya Business Park
Sevenoaks
Size 25,000 sq ft plus 4,000 sq ft mezzanine
Programme 16 weeks
"I must say it’s been a pleasure working with you and your team….caring, professional, polite and fun to work with"










SCOPE OF WORKS
Combining two industrial units into one - Specialist welding zone - New magneto room - Humidity control - Repurposing of donkey crane - New mezzanine - Mechanical - Electrical Works - Decorations - Partitioning - Fire detection - New flooring
WIKA commissioned 3-Space (UK) Ltd to assist them with their complex project of amalgamating their Swanley and Redhill operations into two new BREEAM rated building in Sevenoaks which they wanted opened up to provide one large building to accommodate their manufacturing process.
The design that 3-Space produced included a 4,000 sq ft mezzanine floor with new fire escape staircase to expand the First Floor and provide a central breakout facility for the staff whilst creating new Calibration Laboratories under the mezzanine. The whole of the warehouse was then set aside and planned for their manufacturing process which included welding bays, CNC machines and lathes together with an overhead gantry crane to assist in moving the heavy tubing through the different processes.
3-Space provided visuals to help WIKA understand the design vision whilst also aiding the management team being able to present the positives of the moves to their staff.